Ejercicios De Pert Cpm Resueltos Pdf May 2026

Buscamos en tabla Z: P(Z ≤ 2) = 0.9772 (97.72%)

| Actividad | Predecesor | Duración (días) | |-----------|------------|-----------------| | A | - | 3 | | B | - | 5 | | C | A | 4 | | D | A | 2 | | E | B, C | 6 | | F | D, E | 3 | ejercicios de pert cpm resueltos pdf

Dibujamos las relaciones. A y B comienzan en el inicio. C y D dependen de A. E depende de B y C. F depende de D y E. Buscamos en tabla Z: P(Z ≤ 2) = 0

(usamos nodos - método de precedencia)

: Cualquier retraso en A, C, E o F alargará el proyecto. Las actividades B y D tienen holgura (2 y 8 días respectivamente) y pueden retrasarse sin afectar el final. Ejercicio 2: PERT con cálculo de probabilidad Enunciado : Un proyecto tiene tres actividades en serie: X → Y → Z. Los tiempos (en semanas) son estimados en PERT: E depende de B y C